新冠肺(fei)炎疫情暴發以來,中國西電集(ji)團(tuan)(tuan)堅持“目(mu)標(biao)不變、任務不減、標(biao)準不降”,統(tong)籌(chou)做好疫情防控和復(fu)工(gong)復(fu)產(chan)(chan)(chan)。目(mu)前,集(ji)團(tuan)(tuan)所屬(shu)制(zhi)造型子企業已100%復(fu)工(gong)復(fu)產(chan)(chan)(chan),員工(gong)到(dao)崗率近99%,生(sheng)產(chan)(chan)(chan)經營秩序逐步恢復(fu),產(chan)(chan)(chan)能(neng)基本達(da)到(dao)90%以上,中國西電集(ji)團(tuan)(tuan)統(tong)籌(chou)所屬(shu)各單位開足(zu)馬力、爭分奪秒促產(chan)(chan)(chan)能(neng)、保(bao)生(sheng)產(chan)(chan)(chan),確保(bao)年度生(sheng)產(chan)(chan)(chan)經營目(mu)標(biao)圓(yuan)滿完(wan)成。
西電西變(bian)統籌做好疫情防控(kong)和生(sheng)產(chan)(chan)(chan)經營(ying)各(ge)(ge)項工(gong)作,緊密跟蹤各(ge)(ge)重點工(gong)程(cheng)項目物料到場情況,積極落(luo)實(shi)原材物料準(zhun)(zhun)備、技術圖紙準(zhun)(zhun)備,保證各(ge)(ge)重點項目有序(xu)生(sheng)產(chan)(chan)(chan)。在(zai)全(quan)體干(gan)部(bu)職工(gong)的(de)共同努力下,“張北(bei)—雄安”1000kV特高壓交流輸變(bian)電工(gong)程(cheng)(張北(bei)站)3臺1000kV可控(kong)電抗器(qi)中(zhong)的(de)首臺產(chan)(chan)(chan)品已(yi)進入試(shi)驗工(gong)序(xu),2臺產(chan)(chan)(chan)品已(yi)完成產(chan)(chan)(chan)品總裝;西藏阿里聯網工(gong)程(cheng)20臺500kV電抗器(qi)已(yi)有6臺產(chan)(chan)(chan)品線(xian)圈已(yi)繞制完工(gong),3臺產(chan)(chan)(chan)品正在(zai)線(xian)圈繞制,2臺產(chan)(chan)(chan)品已(yi)完成疊裝。
西開(kai)電氣(qi)將四(si)川雅礱江楊(yang)房(fang)溝等10個重點客戶(hu)的(de)(de)21 個項目列為2020年“1號”工(gong)(gong)程,各黨支部(bu)充(chong)分發(fa)揮黨員突擊(ji)隊引領作用,帶領團隊迎難而(er)上、攻堅克(ke)難,解決生產(chan)過程中(zhong)遇到的(de)(de)難點問題,確保(bao)“1號工(gong)(gong)程”有序(xu)生產(chan)安裝(zhuang),為項目產(chan)品(pin)如(ru)期履(lv)約(yue),保(bao)證企業(ye)生產(chan)經營目標的(de)(de)實(shi)現奠定(ding)了基(ji)礎。目前,西開(kai)電氣(qi)承擔的(de)(de)四(si)川雅礱江楊(yang)房(fang)溝550kV GIS主(zhu)要部(bu)件裝(zhuang)配、試(shi)驗已(yi)經過半,為工(gong)(gong)程如(ru)期履(lv)約(yue)打下(xia)了堅實(shi)基(ji)礎,126kVGIS伊(yi)朗典型(xing)間(jian)隔(ge)站共計8個間(jian)隔(ge)完(wan)成(cheng)了全部(bu)的(de)(de)裝(zhuang)配任務。
西(xi)電(dian)電(dian)力系(xi)統承(cheng)接的陜(shan)北-湖北±800kV特高壓直流(liu)(liu)輸電(dian)工程(cheng)陜(shan)北換流(liu)(liu)站4套(tao)VBE控制柜生產裝配工作已完成(cheng)90%,換流(liu)(liu)閥(fa)絕緣型(xing)式(shi)試驗(yan)已順利完成(cheng),試驗(yan)閥(fa)塔拆卸工作正在(zai)進(jin)行中(zhong),即將開展工程(cheng)用換流(liu)(liu)閥(fa)組件(jian)的批量生產。
寶(bao)(bao)光(guang)(guang)股份(fen)(fen)自(zi)(zi)復(fu)工(gong)(gong)復(fu)產(chan)以來,累計完成(cheng)生產(chan)訂(ding)單(dan)598 個,完成(cheng)產(chan)品數量67569只。寶(bao)(bao)光(guang)(guang)股份(fen)(fen)C產(chan)品制造(zao)部復(fu)工(gong)(gong)期間完成(cheng)西(xi)開(kai)有限急需12只高電(dian)壓高等級(ji)BD口126滅弧室生產(chan)任(ren)務(wu);寶(bao)(bao)光(guang)(guang)股份(fen)(fen)精密陶(tao)瓷(ci)公(gong)司(si)與施耐德(廈門)、韓國(guo)飛(fei)世(shi)龍(long)等客戶各(ge)達(da)成(cheng)萬件陶(tao)瓷(ci)產(chan)品訂(ding)單(dan)備(bei)貨,精密陶(tao)瓷(ci)氣體分公(gong)司(si)整個疫(yi)情期間持續(xu)供應(ying)寶(bao)(bao)雞地(di)區各(ge)醫院、衛生院瓶裝醫用氧氣,為寶(bao)(bao)雞地(di)區疫(yi)情防控提(ti)供了有力保(bao)障。西(xi)電(dian)寶(bao)(bao)雞電(dian)氣為減少人員聚集,優先開(kai)動(dong)自(zi)(zi)動(dong)化鈑金加工(gong)(gong)設備(bei)和開(kai)關柜自(zi)(zi)動(dong)裝配線,分階段組織(zhi)生產(chan),目前(qian),該(gai)司(si)到(dao)產(chan)能達(da)到(dao)95%。
西開有(you)(you)限多個工(gong)程(cheng)(cheng)(cheng)都在(zai)按進(jin)(jin)度有(you)(you)序推(tui)進(jin)(jin):青海-河南±800千伏特高壓直流(liu)工(gong)程(cheng)(cheng)(cheng)的LW15A-550型550kV濾波器斷路(lu)器完成(cheng)(cheng)所有(you)(you)試驗,正在(zai)按計(ji)劃進(jin)(jin)行成(cheng)(cheng)套(tao);云貴互聯通道(dao)工(gong)程(cheng)(cheng)(cheng)的直流(liu)偏磁測量裝(zhuang)(zhuang)置順利發貨;菲律賓直流(liu)項目(mu)的20臺LW25-252柱式斷路(lu)器正在(zai)進(jin)(jin)行裝(zhuang)(zhuang)配,目(mu)前已(yi)完成(cheng)(cheng)18臺,計(ji)劃21日(ri)前完成(cheng)(cheng)全(quan)部(bu)20臺產品的裝(zhuang)(zhuang)配工(gong)作;江蘇10kV柔直工(gong)程(cheng)(cheng)(cheng)產品的安裝(zhuang)(zhuang)工(gong)作正在(zai)如火如荼的進(jin)(jin)行;浙江嘉興輸變電工(gong)程(cheng)(cheng)(cheng)正在(zai)進(jin)(jin)行分裝(zhuang)(zhuang)。
西(xi)(xi)電(dian)常變(bian)青海-河南、雅中(zhong)-江西(xi)(xi)±800千伏特高壓直(zhi)流,張北柔性直(zhi)流等(deng)一批國(guo)家重點(dian)工程也在(zai)緊鑼密鼓的制造(zao)中(zhong)。其中(zhong):14臺(tai)(tai)青海-河南換流變(bian)產(chan)品,前4臺(tai)(tai)±400和前5臺(tai)(tai)±200產(chan)品已(yi)完(wan)成裝配并(bing)順利通(tong)過試驗,第(di)11臺(tai)(tai)產(chan)品已(yi)裝配完(wan)成等(deng)待試驗,第(di)12產(chan)品已(yi)經完(wan)成器(qi)身(shen)裝配,正(zheng)在(zai)器(qi)身(shen)的干燥階段,第(di)13、14臺(tai)(tai)產(chan)品正(zheng)在(zai)器(qi)身(shen)的裝配。雅中(zhong)-江西(xi)(xi)第(di)1臺(tai)(tai)產(chan)品線(xian)(xian)圈(quan)(quan)組裝完(wan)畢、鐵心正(zheng)在(zai)疊裝、油箱六面體制作(zuo)(zuo)中(zhong),第(di)2臺(tai)(tai)產(chan)品正(zheng)在(zai)線(xian)(xian)圈(quan)(quan)繞(rao)制。其他國(guo)家重點(dian)工程項目關鍵設備的制造(zao)工作(zuo)(zuo)也正(zheng)在(zai)有(you)序推進中(zhong)。
西電(dian)避(bi)雷器完成張北(bei)-雄安(an)1000kV特高壓工程百萬伏避(bi)雷器工程、青海-河南±800kV特高壓直流輸電(dian)工程、錦(jin)蘇±800千伏以及(ji)青海海南站750kV等國家重(zhong)點工程所需的避(bi)雷器產品(pin)的制造、出廠試驗和(he)包裝。預計到本月底可實現入庫總產值3200萬,為實現全年生產經營目標做出應(ying)有貢獻(xian)。
西電(dian)西容承擔(dan)的青海-河南±800kV特高壓直(zhi)流(liu)(liu)工(gong)程(cheng)2200余(yu)臺單元(yuan)電(dian)容器現已(yi)(yi)全部完(wan)成生產(chan)(chan);菲(fei)(fei)律(lv)(lv)賓直(zhi)流(liu)(liu)工(gong)程(cheng)的4400臺單元(yuan)電(dian)容器已(yi)(yi)全部生產(chan)(chan)完(wan)畢,正在進行裝箱配(pei)平(ping)工(gong)作,可確保4月10日LALA站(zhan)、6月底DUMANJUG站(zhan)產(chan)(chan)品(pin)按(an)期交貨,菲(fei)(fei)律(lv)(lv)賓項目的互(hu)感(gan)器產(chan)(chan)品(pin)技術準(zhun)備(bei)也已(yi)(yi)完(wan)成,即將(jiang)投入生產(chan)(chan);陜北-武(wu)漢±800kV特高壓直(zhi)流(liu)(liu)工(gong)程(cheng)產(chan)(chan)品(pin)已(yi)(yi)完(wan)成小批試(shi)制(zhi),將(jiang)投入批量(liang)生產(chan)(chan)。
西電光電纜(lan)全面確(que)保防(fang)疫(yi)、復工“兩手(shou)抓、兩不誤”,確(que)保企業年度生(sheng)產(chan)經營目標按計劃實現,復工后生(sheng)產(chan)西安地鐵(tie)(tie)五號線1期(qi)、2期(qi)和鹽通鐵(tie)(tie)路等重點項目共計500余公里,基(ji)本恢(hui)復到疫(yi)情發(fa)生(sheng)前的(de)水平。
西電西材從復(fu)工以來至2月底,產品入庫產值576萬元(無稅),產量298噸,為全面(mian)完(wan)成生產經營目標奠定良好的基礎(chu)。